Kielbasa Kid: One companies website that is selling off plan apartments in this area details the highway extension as being a 'few' years away. Where I come from a few usually means 1 more than a couple which would mean around 3 years. Let me put it this way: Warsaw airport's Terminal 2 was supposed to open in 2005. Because of delay in the tendering process, construction actually started in 2005. It was then supposed to open in April 2006. However, due to a variety of cock-ups, it actually opened in late 2008. Warsaw's second airport, Modlin, was supposed to open in mid-2005. It is now scheduled for opening in late 2010. The A1 motorway (from Gdansk to Katowice) was started in 2005 and should be some 600km long. As of November, 2008, about one-fifth (106.4 km) of the motorway had been completed. That includes a 17.5 km stretch near Łódź, was built between 1978 and 1989. Current proposed finishing date is 2014....
|